    Default Force command to update REPORTS

    There is any command to force the update of reports?

    Like refresh full or something that give to me the information until the last moment.

  2. #2
    Untangle Ninja mrunkel's Avatar
    Join Date
    Jul 2008
    Posts
    3,040

    Default

    Reports only operate on the previous days data, so the answer is no. You can't run a report on a partial day.
    m.


    Big Frickin Disclaimer:
    While I'm pretty sure, I can't guarantee that I know what I'm doing. There might be a better way to do this, and this way might actually suck. Make sure you understand the implications of what you're doing before trying to follow these directions.

    It often helps troubleshooting if you have a good network map. Look here if you want my advice on how to draw one.
    Attention: Support and help on the Untangle Forums is provided by volunteers and community members like yourself.
    If you need Untangle support please call or email support@untangle.com

  3. #3
    Untanglit
    Join Date
    Aug 2010
    Posts
    23

    Default Report running...

    Hey mrunkel - I would assume your stuff is run by a cron job, couldn't your boy kick off a cron manually / early?

    That would be a nice feature, I have to wait 24 hours to get data. What about another method? Where does the reporting data live? Is it a MySQL db? Maybe we could query that and he could write his own report with a php web server and a mysql connect?

    Just trying to think out of the box. Reporting does seem to be lacking but I haven't had the opportunity myself to fully get into it. What I have seen though it seems to be lacking.

    Thanks and keep up the great work with Untangle!

  4. #4
    Untangler jcoffin's Avatar
    Join Date
    Aug 2008
    Location
    Lake Tahoe
    Posts
    9,805

    Default

    There is a way to run the current day report (Midnight - now).

    **Warning** This is not recommended to be used frequently or during work hours as it puts quite a load on the box while processing the logs. Users behind the box could experience delays reaching Internet sites.

    On the terminal type /usr/lib/python2.5/reports/process.py --date=<tomorrow's date>

    i.e. /usr/lib/python2.5/reports/process.py --date=2010-08-12

    This will provide the report for today from Midnight to when the command was executed.

  5. #5
    Untangle Ninja dwasserman's Avatar
    Join Date
    Jun 2008
    Location
    Argentina
    Posts
    4,367

    Default

    Quote Originally Posted by jcoffin View Post
    There is a way to run the current day report (Midnight - now).

    **Warning** This is not recommended to be used frequently or during work hours as it puts quite a load on the box while processing the logs. Users behind the box could experience delays reaching Internet sites.

    On the terminal type /usr/lib/python2.5/reports/process.py --date=<tomorrow's date>

    i.e. /usr/lib/python2.5/reports/process.py --date=2010-08-12

    This will provide the report for today from Midnight to when the command was executed.
    And the schedule midnight report overwrite this partial report? Or we can obtain 2 partial reports?
    The world is divided into 10 kinds of people, who know binary and those not

  6. #6
    Untangle Junkie dmorris's Avatar
    Join Date
    Nov 2006
    Location
    San Carlos, CA
    Posts
    17,747

    Default

    Quote Originally Posted by dwasserman View Post
    And the schedule midnight report overwrite this partial report?
    Yes, it will be overwritten.
    Attention: Support and help on the Untangle Forums is provided by volunteers and community members like yourself.
    If you need Untangle support please call or email support@untangle.com

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  

SEO by vBSEO 3.6.0 PL2